Building Project Update: It’s “full steam ahead” this summer
July, 2010…While students and teachers kick back and enjoy the summer, construction workers are kicking into high gear as Liberty’s building project nears completion. Many elements of the project will be finished and ready for students when they return in the fall. The new media center and greeting lobby at the elementary school will be completed in December 2010.
At the elementary school, the following work will be completed this summer:
• the eight-classroom addition will be tiled, painted and all windows and doors will be installed;
• bathroom renovations and window replacements in the rest of the building will continue throughout the summer;
• kitchen equipment will be installed and tested in July;
• asbestos removal will be completed in July;
• a new drop-off loop at the front of the elementary school is nearing completion; and
• the new elementary administrative offices will be ready by September.
At the high school:
• the media center will be finished for the opening of the school year;
• the girls’ and boys’ locker room is being renovated;
• asbestos removal will be completed in July, which will allow for the renovation of the new high school main office, auditorium vestibule and science laboratories.
If you have questions about the building project, please contact the district administration office at 845-292-6990.
The eight-classroom addition to the Liberty Elementary School nears completion in June 2010.
|